I-75 Bridge Widenings and Replacements
Marion County, Florida

This project involved replacing three existing bridges and widening six others. All of the bridge construction had to be performed while maintaining two lanes of traffic in each direction on I-75. This required detailed construction phasing plans.

The bridge replacements required extensive use of soil anchored sheet pile retaining walls to accommodate the phased construction of these bridges. Also, existing structures were analyzed for the changes in design loads due to the widenings. Utility adjustment plans were also included.